nerdexam
PMIPMI

PMP · Question #845

PMP Question #845: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #845. The question stem and answer options stay visible for context.

Submitted by satoshi_tk· Apr 18, 2026Process

Question

A project manager has experience working with a specific provider that has been requested for an upcoming project. This provider often fails to meet deliverable dates; however it is the only company with the specific experience required for the project. What should the project manager do during the planning phase?

Options

  • AEncourage the provider to work overtime with no additional costs to the project.
  • BHire resources to obtain knowledge about the provider's specific capabilities.
  • CAdd penalty clauses to the contract and update the risk register.
  • DContract another provider with less experience and give them a chance to provide the

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Risk Management#Procurement#Contract Terms#Project Planning
Full PMP PracticeBrowse All PMP Questions