PMP · Question #837

A project manager writes to the receiving organization to inform them that all acceptance activities are completed with success and it's time to initiate handover. The receiving manager replies that t

The correct answer is C. Inform the project sponsor of the two-week delay and replan activities to minimize delays.. The project manager should inform the project sponsor of the delay and then replan activities to minimize the impact of the two-week delay in handover.

Submitted by lucia.co· Apr 18, 2026Process

Question

A project manager writes to the receiving organization to inform them that all acceptance activities are completed with success and it's time to initiate handover. The receiving manager replies that the team will not be ready for the handover procedure for another two weeks. What should the project manager do?

Options

  • AIssue an internal change request to secure the resources for an additional two weeks.
  • BRequest that the receiving manager issue a change request to prolong the project by two weeks.
  • CInform the project sponsor of the two-week delay and replan activities to minimize delays.
  • DDeliver to the receiving manager on time, who can then make a knowledge transfer to their team.

How the community answered

(27 responses)
  • A
    11% (3)
  • B
    4% (1)
  • C
    81% (22)
  • D
    4% (1)

Why each option

The project manager should inform the project sponsor of the delay and then replan activities to minimize the impact of the two-week delay in handover.

AIssue an internal change request to secure the resources for an additional two weeks.

Issuing an internal change request is a detailed step, but informing the sponsor and understanding the broader impact comes first.

BRequest that the receiving manager issue a change request to prolong the project by two weeks.

While a change request might be needed, the project manager should take responsibility for initial assessment and informing the sponsor, not just delegate the request to the receiving manager.

CInform the project sponsor of the two-week delay and replan activities to minimize delays.Correct

A two-week delay in handover impacts the project schedule, resources, and potentially costs, constituting a significant deviation from the plan. The project sponsor needs to be immediately informed as they are ultimately accountable for the project's success and timeline. Following this, the project manager must actively replan activities to mitigate the impact of this delay, such as reassigning resources or adjusting the final closure tasks, to minimize overall project prolongation.

DDeliver to the receiving manager on time, who can then make a knowledge transfer to their team.

Delivering on time when the receiving team isn't ready would lead to an unsuccessful handover and potentially a lack of adoption or proper functioning of the project deliverables.

Concept tested: Managing project delays and stakeholder communication

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok/current

Topics

#Project Closure#Stakeholder Communication#Schedule Management#Issue Resolution