nerdexam
PMIPMI

PMP · Question #820

PMP Question #820: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #820. The question stem and answer options stay visible for context.

Submitted by andres_qro· Apr 18, 2026Process

Question

A labor union contract negotiation is delaying the completion of a project to build a new manufacturing plant. Because the labor contract was due for renewal this year, the project manager documented the negotiation process as a risk to the project. The project was about to start the first phase of equipment installation at the plant when the negotiation began. How should the project manager address the situation?

Options

  • AAcquire contract resources and submit a change request for the cost impact.
  • BEscalate the issue to the steering committee to ask for mitigation support.
  • CLog the issue and follow the planned actions in the risk response plan.
  • DMeet with the project team to determine options for risk mitigation.

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Risk Management#Issue Management#Risk Response Planning
Full PMP PracticeBrowse All PMP Questions