PMIPMI
PMP · Question #806
PMP Question #806: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #806. The question stem and answer options stay visible for context.
Submitted by fatima_kr· Apr 18, 2026Process
Question
An unforeseen event has shut down public works projects for 4 weeks. Activities on the critical path will fall behind based on the project schedule. What should the project manager do?
Options
- AAdd 4 additional weeks to the schedule and request additional resources.
- BAsk the sponsor to obtain a special work permit to continue work.
- CCrash the resource management plan to keep the schedule on track.
- DReview the project management plan to see the impact of the possible delay.
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Risk Management#Schedule Management#Project Management Plan#Impact Analysis