nerdexam
PMIPMI

PMP · Question #783

PMP Question #783: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #783. The question stem and answer options stay visible for context.

Submitted by femi9· Apr 18, 2026Process

Question

The programming activities of a project were planned to last 35 days per module, but the programming of the first module has taken 45 days. What should the project manager do?

Options

  • AEvaluate the situation and identify ways to compress the schedule without impacting baselines.
  • BAsk the team to work overtime to complete the deliverable on time.
  • CSubmit a change request to the project sponsor to change the schedule.
  • DCheck the scope to verify if there is scope creep and get the project on schedule.

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Schedule Management#Schedule Variance#Corrective Action#Baseline Management
Full PMP PracticeBrowse All PMP Questions