nerdexam
PMIPMI

PMP · Question #775

PMP Question #775: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #775. The question stem and answer options stay visible for context.

Submitted by lukas.cz· Apr 18, 2026Process

Question

A project's customer is furious. When the customer arrived at the project site, they discovered that one of their requirements was not met. What should the project manager do?

Options

  • ADiscuss and agree with the customer to implement the missing requirement
  • BRefer to the requirements traceability matrix and analyze the requirement
  • CConsult the scope management plan with the customer to understand the gap
  • DAnalyze the benefits management plan and implement the needed change

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Requirements Management#Scope Management#Requirements Traceability Matrix#Issue Analysis
Full PMP PracticeBrowse All PMP Questions