nerdexam
PMIPMI

PMP · Question #764

PMP Question #764: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #764. The question stem and answer options stay visible for context.

Submitted by rachelw· Apr 18, 2026Process

Question

A project manager entered into a contract with a vendor to build a new system. During the acceptance test stage, the project manager noticed that the system quality was not satisfactory. How should the project manager support their claim to the vendor?

Options

  • AShare unsuccessful results from previous projects with a similar scope
  • BProvide the failed test results along with the agreed-upon acceptance criteria
  • CShow that the acceptance criteria were changed by the vendor without approval.
  • DDocument in the risk log that the issues in the system were already identified

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Quality Management#Procurement Management#Acceptance Criteria#Contract Management
Full PMP PracticeBrowse All PMP Questions