PMP · Question #761
A system migration project is in its closing stage. The project manager is being pressured to close the project. The project manager communicated to all stakeholders; however, the last department to…
The correct answer is C. Close out the project and tell the manager to open a service desk ticket. In the project closing stage, if a department claims non-receipt of migration notification, the project manager should ensure all project-related activities are completed and direct any remaining operational issues to the appropriate support channel, such as a service desk.
Question
A system migration project is in its closing stage. The project manager is being pressured to close the project. The project manager communicated to all stakeholders; however, the last department to migrate indicated that they have not received the notification. What should the project manager do?
Options
- AReport the issue during the next status meeting at the end of the week
- BEscalate the issue to the project sponsor and upper management
- CClose out the project and tell the manager to open a service desk ticket
- DLog the issue and assign it to the project team member(s)
How the community answered
(35 responses)- A3% (1)
- B3% (1)
- C86% (30)
- D9% (3)
Why each option
In the project closing stage, if a department claims non-receipt of migration notification, the project manager should ensure all project-related activities are completed and direct any remaining operational issues to the appropriate support channel, such as a service desk.
Waiting until the next status meeting would delay resolution of an operational issue and may not be appropriate for a project in its closing stage.
Escalating to the project sponsor and upper management is generally for significant project impediments or strategic issues, not for a communication oversight at the operational level during project closure.
In the closing stage of a project, the project manager's primary focus is formal project closure, including transferring deliverables and outstanding issues to operational support. If a department claims they didn't receive notification, and the project manager has already communicated to all stakeholders, this indicates an operational issue post-migration, which should be handled through a service desk ticket rather than delaying project closure.
Logging the issue and assigning it to a project team member would prolong the project and blur the lines between project and operational responsibilities, especially if the migration is already complete for that department.
Concept tested: Project closure and transition to operations
Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok