PMIPMI
PMP · Question #758
PMP Question #758: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #758. The question stem and answer options stay visible for context.
Submitted by amina.ke· Apr 18, 2026Process
Question
During iteration two of a project with two teams (A and B), the project manager is concerned that there are two critical activities from team A that must be started in iteration four. Additionally, these two activities are dependent on an activity from team B that has not yet been prioritized. What should the project manager do?
Options
- ACancel the current iteration and reschedule it with the dependent activity.
- BInclude the dependent activity in the current iteration for team B.
- CEnsure team B prioritizes the dependent activity in iteration three.
- DAssign the two critical activities to team B in iteration two.
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Agile Planning#Dependency Management#Prioritization#Iteration Management