PMIPMI
PMP · Question #749
PMP Question #749: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #749. The question stem and answer options stay visible for context.
Submitted by parkjh· Apr 18, 2026Process
Question
A project manager has been assigned to a new project that will be delivered using an agile framework. The sponsor is asking for a cost estimation to build the business case. What should the project manager do?
Options
- AEnsure the client representative is involved in the estimation.
- BEnsure that a 20% contingency is included in the estimation.
- CReview the completion costs of similar projects.
- DReview the lessons learned from similar projects.
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Cost Estimation#Agile Planning#Analogous Estimating#Business Case