nerdexam
PMIPMI

PMP · Question #745

PMP Question #745: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #745. The question stem and answer options stay visible for context.

Submitted by tom_us· Apr 18, 2026Process

Question

A project manager is using a subcontractor for mobile application development. When the project team tests the application, they realize it does not comply with the new company user-interface standards. Even though these new standards were not included in the statement of work (SOW), the subcontractor agrees to the additional scope as long as payment for this additional work is paid immediately. What should the project manager do?

Options

  • ANegotiate new pricing based on the revised estimations from the subcontractor that reflect the
  • BInitiate a change request and review the contract to evaluate the payment options before
  • CDeny the subcontractor's payment request, because the product does not comply with the project
  • DInitiate a change to incorporate an immediate payment milestone in the contract as per the

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Change Management#Procurement Management#Contract Management#Scope Management
Full PMP PracticeBrowse All PMP Questions