PMP · Question #745
PMP Question #745: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #745. The question stem and answer options stay visible for context.
Question
A project manager is using a subcontractor for mobile application development. When the project team tests the application, they realize it does not comply with the new company user-interface standards. Even though these new standards were not included in the statement of work (SOW), the subcontractor agrees to the additional scope as long as payment for this additional work is paid immediately. What should the project manager do?
Options
- ANegotiate new pricing based on the revised estimations from the subcontractor that reflect the
- BInitiate a change request and review the contract to evaluate the payment options before
- CDeny the subcontractor's payment request, because the product does not comply with the project
- DInitiate a change to incorporate an immediate payment milestone in the contract as per the