nerdexam
PMIPMI

PMP · Question #718

PMP Question #718: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #718. The question stem and answer options stay visible for context.

Submitted by suresh_in· Apr 18, 2026People

Question

A project manager has been assigned to an emergency project that must be completed within the next few weeks. The project manager realizes this will have an impact on the local community. As the work is near a school, the project manager has engaged with them to understand their needs. How should the project manager ensure the work continues smoothly?

Options

  • APostpone the required work on the project until school holidays begin
  • BContinue the work as planned and inform the school when the project team arrives on-site
  • CAdvise the school to close for the duration of the project work
  • DLiaise with the school to include nonworking project hours during school start and finish times

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Stakeholder Engagement#Communication Management#Conflict Resolution#Negotiation
Full PMP PracticeBrowse All PMP Questions