nerdexam
PMIPMI

PMP · Question #705

PMP Question #705: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #705. The question stem and answer options stay visible for context.

Submitted by mike_84· Apr 18, 2026Process

Question

A project manager leads a software development project in a hybrid environment. During project planning, the project manager identified a risk where a technical resource for a critical path item may not be available when needed. One week before the resource is needed, the technical engineer had a personal emergency and had to take a leave. What should the project manager do next?

Options

  • AConsult the risk register for an appropriate planned risk response and implement.
  • BRevise the project management plan and move the task to a time when the technical resource will
  • CReview the business requirement with stakeholders and exclude the task assigned to the
  • DUpdate the lessons learned report and the risk log to reflect that this risk has materialized.

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Risk Management#Risk Register#Planned Risk Response
Full PMP PracticeBrowse All PMP Questions