PMP · Question #700

PMP Question #700: Real Exam Question with Answer & Explanation

The correct answer is B: Add penalty clauses to the contract and update the risk register.. Given a sole-source provider with a history of missed deadlines, the project manager should proactively mitigate this known risk by incorporating penalty clauses into the contract and documenting the risk in the risk register.

Submitted by yousef_jo· Apr 18, 2026Process

Question

A project manager has experience working with a specific provider that has been requested for an upcoming project. This provider often fails to meet deliverable dates; however, it is the only company with the specific experience required for the project. What should the project manager do during the planning phase?

Options

  • AHire resources to obtain knowledge about the provider's specific capabilities.
  • BAdd penalty clauses to the contract and update the risk register.
  • CEncourage the provider to work overtime with no additional costs to the project.
  • DContract another provider with less experience and give them a chance to provide the

Explanation

Given a sole-source provider with a history of missed deadlines, the project manager should proactively mitigate this known risk by incorporating penalty clauses into the contract and documenting the risk in the risk register.

Common mistakes.

  • A. Hiring resources to gain knowledge about the provider's capabilities is unlikely to solve the issue of missed deadlines and adds unnecessary cost and complexity.
  • C. Encouraging overtime without additional cost is an unrealistic expectation for a third-party provider and does not address the underlying issue or mitigate the risk effectively.
  • D. Contracting another less experienced provider is not a viable option, as the question states the requested provider is the 'only company with the specific experience required.'

Concept tested. Risk management and contract negotiation in project management

Reference. https://www.pmi.org/learning/library/risk-management-strategies-techniques-6260

Topics

#Risk Management#Procurement Management#Contract Management#Planning Phase