nerdexam
PMIPMI

PMP · Question #64

PMP Question #64: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #64. The question stem and answer options stay visible for context.

Submitted by helene.fr· Apr 18, 2026Process

Question

During a project's initiation phase, a lessons learned sharing session was held with the team from another project. Low construction productivity was discussed as a potential delay to project completion. What should the project manager do next?

Options

  • ADiscuss this issue with the project sponsor to request additional funding to implement mitigation
  • BPrequalify contractors with proven track records to eliminate productivity concerns
  • CAdd construction productivity to the risk register and develop a mitigation strategy for site
  • DHire a construction management consultant to develop a comprehensive site execution plan

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Risk Management#Lessons Learned#Risk Register#Mitigation Planning
Full PMP PracticeBrowse All PMP Questions