Submitted by valeria.br· Apr 18, 2026Process
Question
During the service procurement process for a strategic project, only one bidder submitted a bid. The price of the offer is significantly large and the project sponsor is not I convinced that the return on investment (ROI) can be achieved. How should the project manager address this issue?
Options
- AAnalyze the bounds of negotiations for project agreements.
- BRe-visit the project charter and seek other alternatives.
- CSpeak with the CEO and ask for their support to approve the offer.
- DProceed and issue the purchase order as this project is important.
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Procurement Management#Business Case#Project Charter#Alternatives Analysis