Question

A project requires the procurement of a large amount of equipment that needs to be on-site before any other activity can begin. The procurement department has a lengthy approval process. What should the project manager do?

Options

  • AContact the vendor that supplied similar equipment for a previous project.
  • BUse the existing equipment and replace it later with the new equipment.
  • CAsk the project sponsor to expedite the vendor selection process.
  • DWork with the procurement team to find alternative options.

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Procurement Management#Stakeholder Engagement#Schedule Management#Process Management