Submitted by haruto_sh· Apr 18, 2026Process
Question
A project manager is managing the transition to operations. The project sponsor wants to ensure that good support is provided to the end users. What should the project manager do?
Options
- AEnsure that comprehensive documentation is handed over.
- BAsk the project team to provide operational support for 1 year.
- CEnsure that knowledge is transferred to the operations team.
- DEnsure that the user guide is detailed and has clear instructions.
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Knowledge Transfer#Project Closure#Transition Management#Operations Handover