A customer is concerned with the quality of the product delivery, as the production deployment is approaching. What should the project manager do next to ensure acceptance of the deliverables?

The correct answer is B. Evaluate the quality checklist for product compliance. To address customer concerns about product quality and ensure acceptance, the project manager should evaluate the quality checklist for product compliance.

Submitted by lars.no· Apr 18, 2026Process

Question

A customer is concerned with the quality of the product delivery, as the production deployment is approaching. What should the project manager do next to ensure acceptance of the deliverables?

Options

  • AVerify the production budget before advancing the product.
  • BEvaluate the quality checklist for product compliance.
  • CReview the approved exit criteria for the product.
  • DTest product integration in accordance with the requirements.

How the community answered

(50 responses)
  • A
    4% (2)
  • B
    72% (36)
  • C
    8% (4)
  • D
    16% (8)

Why each option

To address customer concerns about product quality and ensure acceptance, the project manager should evaluate the quality checklist for product compliance.

AVerify the production budget before advancing the product.

Verifying the production budget is a financial control and does not directly address the customer's concerns regarding the product's quality or fitness for acceptance.

BEvaluate the quality checklist for product compliance.Correct

An agile quality checklist defines specific criteria and standards that the product must meet for acceptance. Evaluating this checklist directly verifies that the product adheres to the agreed-upon quality requirements, thereby addressing customer concerns and ensuring deliverable acceptance.

CReview the approved exit criteria for the product.

Reviewing approved exit criteria primarily focuses on conditions for project closure rather than verifying the ongoing quality of the product's deliverables for customer acceptance.

DTest product integration in accordance with the requirements.

While testing product integration is part of ensuring quality, evaluating the comprehensive quality checklist confirms compliance against all established quality metrics for final acceptance.

Concept tested: Agile quality assurance and acceptance criteria

Source: https://www.pmi.org/pmbok-guide-standards/agile

Topics

#Quality Management#Deliverable Acceptance#Quality Control#Compliance