PMP · Question #53
PMP Question #53: Real Exam Question with Answer & Explanation
The correct answer is B: Ask the team member to submit a formal change request. Even if a suggestion appears to add value without negative impact, any proposed change to product attributes should follow a formal change control process.
Question
A project manager receives a suggestion from a team member for improving the product attributes without impacting the schedule or cost. This will add value to the project and the customer. What should the project manager do?
Options
- AReject the suggestion and ask the team member to focus on executing the plan
- BAsk the team member to submit a formal change request
- CAccept the suggestion as it has no impact on the project
- DAsk another team member to validate the impacts of the suggestion
Explanation
Even if a suggestion appears to add value without negative impact, any proposed change to product attributes should follow a formal change control process.
Common mistakes.
- A. Rejecting a potentially valuable suggestion without evaluation discourages team member engagement and innovation.
- C. Accepting a suggestion without a formal process bypasses change control, risking undocumented scope changes and potential unforeseen impacts on project baselines.
- D. While validation is important, it is part of the change request process; asking only one other team member for validation is insufficient and bypasses the formal process.
Concept tested. Project change control process
Reference. https://www.pmi.org/pmbok-guide-standards/foundational/pmbok
Topics
Community Discussion
No community discussion yet for this question.