PMP · Question #53

A project manager receives a suggestion from a team member for improving the product attributes without impacting the schedule or cost. This will add value to the project and the customer. What…

The correct answer is B. Ask the team member to submit a formal change request. Even if a suggestion appears to add value without negative impact, any proposed change to product attributes should follow a formal change control process.

Submitted by yasin.bd· Apr 18, 2026Process

Question

A project manager receives a suggestion from a team member for improving the product attributes without impacting the schedule or cost. This will add value to the project and the customer. What should the project manager do?

Options

  • AReject the suggestion and ask the team member to focus on executing the plan
  • BAsk the team member to submit a formal change request
  • CAccept the suggestion as it has no impact on the project
  • DAsk another team member to validate the impacts of the suggestion

How the community answered

(14 responses)
  • A
    7% (1)
  • B
    86% (12)
  • D
    7% (1)

Why each option

Even if a suggestion appears to add value without negative impact, any proposed change to product attributes should follow a formal change control process.

AReject the suggestion and ask the team member to focus on executing the plan

Rejecting a potentially valuable suggestion without evaluation discourages team member engagement and innovation.

BAsk the team member to submit a formal change requestCorrect

In project management, even seemingly beneficial changes must undergo a formal change request process to ensure proper documentation, impact analysis, and stakeholder approval, maintaining project control and preventing scope creep. This ensures that all potential downstream effects are considered and formally accepted before implementation.

CAccept the suggestion as it has no impact on the project

Accepting a suggestion without a formal process bypasses change control, risking undocumented scope changes and potential unforeseen impacts on project baselines.

DAsk another team member to validate the impacts of the suggestion

While validation is important, it is part of the change request process; asking only one other team member for validation is insufficient and bypasses the formal process.

Concept tested: Project change control process

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#Change management#Integrated change control#Scope management#Value delivery

Community Discussion

8
Viktor S.Viktor S.Dec 2, 2025

B is correct. Even with zero impact to schedule or cost, any change to product attributes goes through Perform Integrated Change Control so the impact gets formally documented and approved, not just accepted on a handshake.

26
Grace U.Grace U.Dec 4, 2025

Agreed on B, and worth adding that even a zero-impact change still needs that paper trail so the update is traceable later if scope creep questions come up during audit or stakeholder review.

0
Yuki V.Yuki V.Nov 19, 2025

B. C is tempting but no change is free, even with zero cost or schedule impact.

5
Viktor S.Viktor S.Nov 21, 2025

Agreed on B, but worth adding that the change review process itself has overhead, which is exactly why the no-impact argument falls apart in practice.

0
Grace U.Grace U.Nov 6, 2025

B. Even free improvements go through change control. Why does PMI want every value-add documented?

3
Bao N.Bao N.Nov 12, 2025

Got B on my exam last month, no change means no CR trips everyone up.

1
Lena V.Lena V.Nov 17, 2025

Picked A. PMI wants disciplined execution, not unsolicited gold plating scope changes.

-2
Yuki V.Yuki V.Nov 19, 2025

Actually it is B. Gold plating is the term PMI uses for adding scope or features beyond what was requested, which is exactly what the question is describing, so that is the concept being tested rather than the response to it.

0