A project manager led the implementation of an electronic invoicing project that has just been completed. The financial manager communicated that the team discovered three invoices with errors. Which two documents should the project manager update as soon as possible? (Choose two.)
Options
- AIssue log
- BRisk register
- CStakeholder register
- DChange log
- EBacklog register