PMP · Question #500
PMP Question #500: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #500. The question stem and answer options stay visible for context.
Question
During project execution, the risk owner is monitoring the critical speed rate of a power engine to eventually trigger the defined risk-response strategy. During the risk assessment and management process phase, it was defined that the power engine has the following characteristics: 1,600 rpm (rate-per-minute) -> stops working and crashes the system 1,500 rpm (rate-per-minute) -> warns of max rate allowed 1,400 rpm (rate-per-minute) -> reduces the power and brakes the engine Which of the following statements is correct?
Options
- A1,600 rpm is a project risk, 1,500 rpm is an event that triggers a response strategy, and 1,400 rpm
- B1,600 rpm is a project issue, 1,500 rpm is an event that triggers a response strategy, and 1,400
- C1,600 rpm is a project issue, 1,500 rpm is a project risk, and 1,400 rpm is an event that triggers a
- D1,600 rpm is an event that triggers a response strategy, 1,500 rpm is a project issue, and 1,400
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.