nerdexam
PMIPMI

PMP · Question #496

PMP Question #496: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #496. The question stem and answer options stay visible for context.

Submitted by tarun92· Apr 18, 2026Process

Question

A project manager has been managing a highly complex project. The project manager has ensured that all of the required tasks have been completed. During a recent external audit. The project manager was informed of a heavy penalty being levied on the project for the latest module that was implemented. What should the project manager have done to ensure that there were no liabilities arising from the recent implementation?

Options

  • AEnsured that all defects identified during testing were resolved before implementation
  • BEnsured that all of the required tasks identified in the scope were completed successfully
  • CEnsured that all documentation was completed post implementation before closing the project
  • DEnsured that all the required approvals were received per the organizational procedures

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Approvals#Compliance Management#Project Governance#Liability Management
Full PMP PracticeBrowse All PMP Questions