A project just kicked off and management's expectation is to ensure that the deliverable of the first iteration helps the marketing team present the product prototype to potential customers. What shou
The correct answer is D. Identify the minimum functionality required for the product. Management expects the first iteration to deliver a product prototype for customer presentation, requiring a focus on essential features to meet this specific goal. The project manager should identify the minimum viable functionality needed.
Question
A project just kicked off and management's expectation is to ensure that the deliverable of the first iteration helps the marketing team present the product prototype to potential customers. What should the project manager do?
Options
- AIncrease the details of the work breakdown structure (WBS) to minimize errors and delays
- BSplit the backlog into phases to ensure that the key features are delivered first
- CAsk the sponsor to prioritize some functionalities of the product
- DIdentify the minimum functionality required for the product
How the community answered
(31 responses)- A6% (2)
- B6% (2)
- C3% (1)
- D84% (26)
Why each option
Management expects the first iteration to deliver a product prototype for customer presentation, requiring a focus on essential features to meet this specific goal. The project manager should identify the minimum viable functionality needed.
Increasing WBS details is more typical for predictive projects and focuses on exhaustive planning, which may hinder the agility needed to quickly deliver a prototype.
Splitting the backlog into phases is a general backlog management technique, but it doesn't specifically address the immediate need to identify the core features for the prototype.
While the sponsor might prioritize, it is the project manager's or product owner's role to lead the identification of the essential functionalities for a specific deliverable, often in collaboration with stakeholders, but not simply 'ask the sponsor to prioritize some functionalities'.
When the goal is to present a product prototype for marketing, the focus should be on delivering the "Minimum Viable Product" (MVP) or Minimum Business Increment (MBI) that provides just enough functionality to satisfy the immediate objective. Identifying this minimum functionality ensures the team focuses on what is most critical for the first iteration's success.
Concept tested: Minimum Viable Product (MVP) / Minimum Business Increment (MBI)
Source: https://www.atlassian.com/agile/scrum/mvp
Topics
Community Discussion
6D is right. Marketing needs something tangible to show customers, so you find the minimum viable functionality and get that built first instead of over-engineering the WBS or slicing the backlog without knowing what actually matters.
D is correct. Management wants something demonstrable fast, which lines up perfectly with the MVP concept the exam loves: identify the minimum functionality required and get that prototype in front of customers.
Leaned toward B first, but marketing prototype means MVP, so D.
D is right but the exam trigger is actually "validate assumptions" not "prototype" alone, so watch for that wording variation.
Leaned toward B first but "minimum functionality" screams MVP so D it is.
D is right because they need an MVP. Anyone know if PMP always ties MVP to agile?