nerdexam
PMIPMI

PMP · Question #438

PMP Question #438: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #438. The question stem and answer options stay visible for context.

Submitted by andreas_gr· Apr 18, 2026Process

Question

Team members are having a discussion with the project manager. In the last retrospective meeting, the team realized that the obsolete equipment could affect the next iteration of the project. The team recommends buying new equipment because it is critical to the success of the final deliverable. What should the project manager do next?

Options

  • ACheck the project budget to verify if there is enough contingency reserve
  • BReview the cost management plan to determine how to address this issue
  • CTell the team members that more equipment is not part of the project's scope
  • DSubmit a change request to increase the budget and buy new equipment

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Cost Management#Project Management Process#Retrospectives#Change Management
Full PMP PracticeBrowse All PMP Questions