PMP · Question #436

PMP Question #436: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #436. The question stem and answer options stay visible for context.

Submitted by chen.hong· Apr 18, 2026Process

Question

In analyzing a project for monthly status reporting, the project manager notices that the schedule performance index (SPI) is 0,75 and the cost performance index (CPI) is 1,25. The project manager must provide the first project status review soon and wants to emphasize that the project is under control. How should the project manager report the project status to key stakeholders?

Options

  • APrepare a detailed presentation for stakeholders on earned value including how it is calculated
  • BReport that the project is behind schedule but that an additional experienced resource can be
  • CPerform a detailed root cause analysis utilizing a pareto chart and fishbone diagrams to
  • DReport that the project is not tracking as expected, but is still under control since the next project

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Earned Value Management (EVM)#Performance Reporting#Stakeholder Communication#Corrective Actions
Full PMP PracticeBrowse All PMP Questions