In analyzing a project for monthly status reporting, the project manager notices that the schedule performance index (SPI) is 0,75 and the cost performance index (CPI) is 1,25. The project manager mus
The correct answer is B. Report that the project is behind schedule but that an additional experienced resource can be. Given an SPI of 0.75 (behind schedule) and CPI of 1.25 (under budget), the project manager should transparently report the schedule delay while proposing a concrete solution, such as adding an experienced resource, to bring the project back on track.
Question
In analyzing a project for monthly status reporting, the project manager notices that the schedule performance index (SPI) is 0,75 and the cost performance index (CPI) is 1,25. The project manager must provide the first project status review soon and wants to emphasize that the project is under control. How should the project manager report the project status to key stakeholders?
Options
- APrepare a detailed presentation for stakeholders on earned value including how it is calculated
- BReport that the project is behind schedule but that an additional experienced resource can be
- CPerform a detailed root cause analysis utilizing a pareto chart and fishbone diagrams to
- DReport that the project is not tracking as expected, but is still under control since the next project
How the community answered
(23 responses)- A17% (4)
- B43% (10)
- C30% (7)
- D9% (2)
Why each option
Given an SPI of 0.75 (behind schedule) and CPI of 1.25 (under budget), the project manager should transparently report the schedule delay while proposing a concrete solution, such as adding an experienced resource, to bring the project back on track.
While earned value is important, a detailed presentation on its calculation might overwhelm stakeholders and distract from the actual status and proposed solutions, especially when the goal is to emphasize control.
An SPI of 0.75 indicates the project is behind schedule, and a CPI of 1.25 indicates it is under budget, which allows for potentially allocating more resources to catch up. Reporting the current status with a proposed solution, like adding an experienced resource to address the schedule delay, is a proactive and transparent way to inform stakeholders while demonstrating control and a plan to mitigate the delay.
Performing a detailed root cause analysis is a necessary step, but it is not the *first* thing to do before reporting the status when a review is imminent; the project manager needs to report the current status and propose immediate actions first.
Simply stating the project is not tracking as expected but "under control" due to the "next project phase" is vague and lacks concrete justification or a plan, especially when the current SPI indicates it's not under schedule control.
Concept tested: Earned Value Management Interpretation and Communication