nerdexam
PMIPMI

PMP · Question #413

PMP Question #413: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #413. The question stem and answer options stay visible for context.

Submitted by deeparc· Apr 18, 2026Process

Question

The project charter was just approved and the project sponsor has given permission to proceed with the project. The program manager has confirmed that one of the requested key resources is also needed on another project at the same time. This will affect project delivery. What should the project manager do?

Options

  • APay overtime to key resource to get the work done outside of working hours
  • BHave a meeting with project manager of the other project to find a resource optimization solution
  • CSpeak with the client to see if the project delivery deadline can be delayed due to resource
  • DTalk to the program manager and about prioritizing this project over other projects so the key

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Resource Management#Conflict Resolution#Stakeholder Collaboration#Resource Optimization
Full PMP PracticeBrowse All PMP Questions