nerdexam
PMIPMI

PMP · Question #397

PMP Question #397: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #397. The question stem and answer options stay visible for context.

Submitted by olafpl· Apr 18, 2026Process

Question

During project execution, the project manager notices that the work performance reports have deteriorated drastically in less than two weeks. The project team in country A is complaining about delays resulting from holidays occurring in country B that have impacted their project team. How should the project manager handle this situation?

Options

  • AImplement crashing to compress the schedule and improve the schedule performance index
  • BImplement fast-tracking to compress the schedule and improve the SPI
  • CPerform conflict management using the project's resource management plan.
  • DReview the risk management plan to evaluate the probability and impact of these delays

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Risk Management#Issue Resolution#Schedule Delays#Work Performance Analysis
Full PMP PracticeBrowse All PMP Questions