nerdexam
PMI

PMP · Question #386

During the design phase of a project, the project manager notices that the schedule performance index (SPI) is 1,8 and the cost performance index (CPI) is 0,1. In a weekly meeting with top management,

The correct answer is B. Stop crashing the schedule. With an SPI of 1.8 (ahead of schedule) and a critically low CPI of 0.1 (severely over budget), the project manager should immediately stop crashing the schedule, which is likely causing the extreme cost overruns.

Submitted by fernanda_arg· Apr 18, 2026Process

Question

During the design phase of a project, the project manager notices that the schedule performance index (SPI) is 1,8 and the cost performance index (CPI) is 0,1. In a weekly meeting with top management, the project manager reports concerns about these indicators. However, the most concerned person was the project sponsor who said that if the trend continues, they will be forced to prematurely close the project. What should the project manager do?

Options

  • AMonitor the project sponsor, but understand that it is normal to spend more money in the design
  • BStop crashing the schedule
  • CManage the project sponsor closely and revise the project's resource management plan to
  • DUse a resource-leveling technique

How the community answered

(36 responses)
  • A
    6% (2)
  • B
    69% (25)
  • C
    8% (3)
  • D
    17% (6)

Why each option

With an SPI of 1.8 (ahead of schedule) and a critically low CPI of 0.1 (severely over budget), the project manager should immediately stop crashing the schedule, which is likely causing the extreme cost overruns.

AMonitor the project sponsor, but understand that it is normal to spend more money in the design

A CPI of 0.1 is never normal in any project phase; it signifies a critical budget problem requiring immediate intervention, not just monitoring.

BStop crashing the scheduleCorrect

A high Schedule Performance Index (SPI > 1) combined with a very low Cost Performance Index (CPI << 1) strongly indicates that the project's schedule is being aggressively accelerated or 'crashed' by throwing excessive resources at it. Stopping this schedule crashing is the immediate and most logical step to mitigate the severe cost issue and prevent project closure.

CManage the project sponsor closely and revise the project's resource management plan to

While sponsor management is ongoing, the immediate technical problem is the catastrophic CPI; revising the resource plan might be a subsequent step, but the first action is to stop the presumed cause of the current problem.

DUse a resource-leveling technique

Resource leveling aims to optimize resource utilization and can sometimes extend the schedule, which is not the immediate concern when the project is already far ahead of schedule but critically over budget due to aggressive acceleration.

Concept tested: Earned Value Management (EVM) interpretation and corrective actions

Topics

#Earned Value Analysis#Cost Performance Index (CPI)#Schedule Performance Index (SPI)#Schedule Compression

Community Discussion

5
Nina C.Nina C.Jun 1, 2026

B is correct. An SPI of 1.8 means you are way ahead of schedule while a CPI of 0.1 means you are burning through cash at a ridiculous rate, which is a classic sign of schedule crashing. Stop crashing the schedule and the costs should come back in line.

17
Fatima Z.Fatima Z.May 24, 2026

A is my pick. Design = spend money now, build later. SPI 1.8 looks great on paper but CPI 0.1 is bleeding cash. Crashing burns budget to save time. Stop the bleeding, let design finish naturally.

-1
Nina C.Nina C.May 25, 2026

Actually it is B. CPI of 0.1 means you are getting almost no value for every dollar spent, so the priority is fixing the cost problem first, and a cost audit is the direct action for that.

0
Brenda K.Brenda K.May 31, 2026

D. SPI 1.8 screams overallocation from crashing, leveling fixes it fast, flag and move on.

-2
Nina C.Nina C.Jun 1, 2026

Actually it is B, because SPI tells you about schedule efficiency, not resource utilization. You would want to look at resource leveling to resolve the overallocation, then update the schedule baseline through the change control process.

0
Full PMP Practice