nerdexam
PMIPMI

PMP · Question #386

PMP Question #386: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #386. The question stem and answer options stay visible for context.

Submitted by fernanda_arg· Apr 18, 2026Process

Question

During the design phase of a project, the project manager notices that the schedule performance index (SPI) is 1,8 and the cost performance index (CPI) is 0,1. In a weekly meeting with top management, the project manager reports concerns about these indicators. However, the most concerned person was the project sponsor who said that if the trend continues, they will be forced to prematurely close the project. What should the project manager do?

Options

  • AMonitor the project sponsor, but understand that it is normal to spend more money in the design
  • BStop crashing the schedule
  • CManage the project sponsor closely and revise the project's resource management plan to
  • DUse a resource-leveling technique

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Earned Value Analysis#Cost Performance Index (CPI)#Schedule Performance Index (SPI)#Schedule Compression
Full PMP PracticeBrowse All PMP Questions