nerdexam
PMIPMI

PMP · Question #37

PMP Question #37: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #37. The question stem and answer options stay visible for context.

Submitted by layla.eg· Apr 18, 2026Process

Question

A project manager is asked to develop maintenance planning software for a power plant. A similar project was executed by another department in the organization that was later closed due to low performance. The project manager is concerned about the project's performance and wants to take action in advance to ensure the project succeeds. What should the project manager do?

Options

  • AContinue executing the project as planned and add more resources if they are required.
  • BEvaluate the project risk and add external experts to address the potential risks.
  • CReview the lessons learned on similar projects so that they do not fall back into the same pattern.
  • DInform the project sponsor about the risk and try to convince them to withdraw from the project.

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Lessons Learned#Organizational Process Assets#Risk Mitigation#Project Planning
Full PMP PracticeBrowse All PMP Questions