PMIPMI
PMP · Question #348
PMP Question #348: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #348. The question stem and answer options stay visible for context.
Submitted by takeshi77· Apr 18, 2026Process
Question
The change control board (CCB) rejects a change request submitted by a subject matter expert (SME). The SME refuses to accept this rejection and does not want to continue the project without the change. What should the project manager have done to avoid this situation?
Options
- ARequested that the sponsor approved the change request first
- BAssessed the change's overall impact to the project before submission
- CEnsured that the change request was aligned with the project scope
- DSubmitted the change request directly to the CCB
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Change Management#Stakeholder Management#Impact Analysis#Conflict Prevention