The correct answer is D: Analyze the requirements that will need to be addressed under the requested method. The project manager should analyze the requirements that will need to be addressed under the requested method, which is Agile approach, and evaluate the impact on the project schedule, cost and quality. This will help to understand how the change in approach will affect the proje
Question
A company is using a predictive approach for the development of a particular component as defined in the scope management plan. Due to regularly changing regulatory requirements, the development team has requested to utilize agile approaches. What should the project manager do about the development team's request?
Options
- AEscalate the request for additional financial resources
- BForward the request to the project management office (PMO) to amend the organizational
- CAsk the project sponsor to obtain approval for implementation of the new approach
- DAnalyze the requirements that will need to be addressed under the requested method
Explanation
The project manager should analyze the requirements that will need to be addressed under the requested method, which is Agile approach, and evaluate the impact on the project schedule, cost and quality. This will help to understand how the change in approach will affect the project and the stakeholders. The project manager should also evaluate if the agile approach is the best fit for the project and the organization.