PMP · Question #285

PMP Question #285: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #285. The question stem and answer options stay visible for context.

Submitted by priya_blr· Apr 18, 2026People

Question

The project sponsor of a major initiative is consistently changing the prioritization of modular work packages. The team is used to three week sprints and is becoming increasingly frustrated with the daily changes in scope. What should the project manager do?

Options

  • ASet up a meeting with the sponsor to explain the importance of keeping a strict sprint cycle.
  • BDecrease the sprint cycle to the average reprioritization request by calculating it in days.
  • CSet up a meeting with the project team and ask for their opinion on what to do.
  • DMove to a Kanban strategy so that work can be reallocated more easily.

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Agile#Stakeholder Management#Scope Management#Communication