Question
A project manager has been asked to participate in the procurement process for a software application that allows customers to buy online e-learning courses. The project manager will take over the project once the supplier has been sourced. What should the project manager do before the project starts?
Options
- AAsk the project sponsor to involve the legal department in the negotiation for the project
- BNotify the project sponsor that the project manager cannot be involved in the agreement
- CInform the project sponsor that once the agreement has been signed, there cannot be any
- DEnsure that the requirements for the project are understood and that the objectives are verified
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Procurement Management#Contract Management#Legal Review#Pre-project Activities