PMIPMI
PMP · Question #24
PMP Question #24: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #24. The question stem and answer options stay visible for context.
Submitted by zhang_li· Apr 18, 2026Process
Question
One phase of a project took much longer than initially anticipated. The key stakeholders expressed their concern regarding a potential project delay. What should the project manager do?
Options
- ARequest additional contingency from the sponsor
- BAdd more float to the overall project schedule
- CExpedite the next phase to reduce slippage
- DOrganize a root cause analysis (RCA) workshop
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Root cause analysis#Schedule management#Problem-solving#Performance monitoring