A project team strongly encourages the project manager to purchase an application that will significantly reduce work time. Without the application, the deadline might be missed. However, the purchase
The correct answer is D. Analyze assumptions and constraints.. When faced with a dilemma involving potential cost increases to meet a deadline, the project manager should first analyze project assumptions and constraints to understand the full impact of available options.
Question
A project team strongly encourages the project manager to purchase an application that will significantly reduce work time. Without the application, the deadline might be missed. However, the purchase will impact the project cost. The sponsor would like to explore a less expensive application that will save the team's time. What should the project manager do?
Options
- ARaise a change request.
- BCreate a decision tree.
- CPurchase the application.
- DAnalyze assumptions and constraints.
How the community answered
(49 responses)- A4% (2)
- B6% (3)
- C12% (6)
- D78% (38)
Why each option
When faced with a dilemma involving potential cost increases to meet a deadline, the project manager should first analyze project assumptions and constraints to understand the full impact of available options.
Raising a change request is premature; the PM first needs to understand the problem fully and analyze alternatives before proposing a specific change.
While a decision tree can be a tool for analysis, the core issue is understanding the project's current state and boundaries (assumptions and constraints) related to this new information.
Purchasing the application immediately without further analysis ignores the sponsor's concern about cost and the potential for a less expensive solution, leading to a potentially suboptimal decision.
Before making a decision or raising a change request, the project manager needs to thoroughly analyze the situation by reviewing project assumptions (e.g., about team efficiency, time required) and constraints (e.g., budget, deadline) to understand the full implications of the purchase options and inform the best path forward.