PMP · Question #191

PMP Question #191: Real Exam Question with Answer & Explanation

The correct answer is C: Create a framework to support project success.. For a new CEO with no project experience wanting to execute projects, the project manager should first recommend establishing a project management framework to ensure project success.

Submitted by carter_n· Apr 18, 2026Process

Question

A startup company has just appointed a CEO that has no prior project experience. The CEO wants to execute projects with their own resources and has appointed a project manager. What should the project manager recommend that the CEO do first?

Options

  • ACreate a framework to justify project execution.
  • BUtilize an agile approach for all upcoming projects.
  • CCreate a framework to support project success.
  • DUtilize a predictive approach for all upcoming projects.

Explanation

For a new CEO with no project experience wanting to execute projects, the project manager should first recommend establishing a project management framework to ensure project success.

Common mistakes.

  • A. While justifying projects is important, a framework for execution and success encompasses more than just justification; it's about the entire project lifecycle and operations.
  • B. Recommending a specific methodology (agile) for all projects without understanding the company's needs, project types, and context is premature and potentially inappropriate.
  • D. Similar to agile, recommending a predictive approach for all projects is also premature without a foundational framework and understanding of diverse project requirements.

Concept tested. Project management framework establishment

Topics

#Project Governance#Organizational Project Management#Project Framework#Organizational Enablement