PMP · Question #171

PMP Question #171: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #171. The question stem and answer options stay visible for context.

Submitted by anna_se· Apr 18, 2026Process

Question

A facility extension project is in the execution stage. There is a project activity to connect the power of all new equipment to an existing facility, Point A, which requires a significant cable length. The construction team found that the power could be connected to Point B and save money. What should the project manager do next?

Options

  • APerform a cost-benefit analysis to evaluate using the Point B option.
  • BAdd the issue to the change log and request additional budget through the change control board
  • CSeek a decision from the construction team after explaining the project budget and schedule
  • DUse the Point B option because it will save the project cost and time.

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Change Management#Cost Management#Alternatives Analysis