PMP · Question #1435
PMP Question #1435: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #1435. The question stem and answer options stay visible for context.
Question
A project manager's transformation project has been delayed due to unexpected issues with the information technology (IT) systems. These issues are likely to impact the project budget, but the project manager is working hard to make ensure there is no impact on the project's schedule and scope. Which two actions should the project manager take before proposing a budget rebaseline to upper management for approval? (Choose two.)
Options
- AConsider schedule compression techniques to shorten or accelerate the schedule duration
- BConsider using resource leveling to more accurately reflect the work commitments of the
- CApply data analysis techniques, variance analysis, and trend analysis.
- DAnalyze the budget based on the revised estimates and responses from similar situations in the
- ERaise a change request with high priority to be discussed in the upcoming governance meetings.
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.