nerdexam
PMIPMI

PMP · Question #143

PMP Question #143: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #143. The question stem and answer options stay visible for context.

Submitted by rania.sa· Apr 18, 2026Process

Question

A project has met the agreed-upon product requirements and is closing. There is time remaining in the schedule and excess budget. The resources are not yet scheduled to move to other projects. Several product champions want to continue adding functionality to the product. What should the project manager do?

Options

  • AUse the remaining time and resources to add additional scope to the project without spending the
  • BEnsure product quality by spending the remaining resources and time on additional quality checks
  • CAcknowledge the project closure criteria has been met and release the remaining budget and
  • DObtain approval from the sponsor to add additional functionality to the project deliverables with

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Project Closure#Scope Management#Resource Management#Project Integration Management
Full PMP PracticeBrowse All PMP Questions