Question

A project sponsor asks the project team to add an enhancement to the project. How should the project manager address this request?

Options

  • AAccept the request because it came from the project sponsor.
  • BRefuse the project sponsor's request because it is out of scope.
  • CCheck if the budget can cover the enhancement.
  • DValidate the proposed change's impact on the project.

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Change control#Change request#Impact analysis#Integrated Change Control