A project manager identifies a risk that has a high probability of occurring. How should the project manager manage this risk?

The correct answer is D. Ask the team to monitor the risk and provide an alert if it becomes an issue.. A project manager has identified a risk with a high probability of occurring.

Submitted by luis.pe· Apr 18, 2026Process

Question

A project manager identifies a risk that has a high probability of occurring. How should the project manager manage this risk?

Options

  • AAssign a qualified team member to be the risk manager for the project.
  • BRemove the user stories associated to that risk and avoid the impact to the project deliverables.
  • CSubmit a change request to transfer the risk to a third party in case it becomes an issue.
  • DAsk the team to monitor the risk and provide an alert if it becomes an issue.

How the community answered

(21 responses)
  • A
    5% (1)
  • B
    10% (2)
  • D
    86% (18)

Why each option

A project manager has identified a risk with a high probability of occurring.

AAssign a qualified team member to be the risk manager for the project.

Assigning a dedicated risk manager for one specific risk is usually an overkill and not a standard response for every high-probability risk; risk management is typically a shared responsibility or handled by the PM.

BRemove the user stories associated to that risk and avoid the impact to the project deliverables.

Removing user stories (implying scope reduction) is an avoidance strategy that might be applicable if the risk is unacceptable and can be fully avoided by changing scope, but it's not the primary or only response for a high probability risk that still needs to be managed.

CSubmit a change request to transfer the risk to a third party in case it becomes an issue.

Transferring a risk to a third party (e.g., insurance, outsourcing) is a valid response, but it typically involves a change request and contract, and it's not the *first* or *only* response, especially if monitoring and mitigation are still options.

DAsk the team to monitor the risk and provide an alert if it becomes an issue.Correct

For risks identified as high probability but not yet actualized, monitoring is a crucial response strategy. Asking the team to monitor the risk ensures ongoing vigilance, allows for early detection if the risk event starts to occur, and enables prompt activation of contingency plans or mitigation efforts if it materializes into an issue.

Concept tested: Risk monitoring and response strategies

Source: https://www.projectmanagement.com/blog-post/10291/Risk-Management-Strategy

Topics

#Risk Management#Risk Monitoring#Risk Response Planning

Community Discussion

No community discussion yet for this question.