PMIPMI
PMP · Question #1349
PMP Question #1349: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #1349. The question stem and answer options stay visible for context.
Submitted by hassan_iq· Apr 18, 2026Process
Question
A newly assigned project manager is reviewing the project management plan and realizes that the project is running behind schedule. What should the new project manager do to address this situation?
Options
- ANegotiate with the project sponsor immediately and establish a new project charter.
- BModify the project management plan and get approval from relevant stakeholders.
- CIssue a change order to the change control board (CCB) and rebaseline the schedule.
- DAdd more resources to recover the schedule without making changes to the baseline.
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Change Management#Schedule Management#Project Management Plan#Corrective Action