nerdexam
PMIPMI

PMP · Question #1340

PMP Question #1340: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #1340. The question stem and answer options stay visible for context.

Submitted by katya_ua· Apr 18, 2026Process

Question

A project manager and project team have brought a project back on track after mapping and removing impediments. During the current sprint, the team reported that an impediment that previously caused major delays has appeared again. The team tried implementing the same mitigation tasks that worked previously. However, the tasks are not having the same result with the impediment. What should the project manager do?

Options

  • AEscalate the issue with an impediment to the project sponsor.
  • BImplement the mitigation plans listed in the organizational process assets (OPAs).
  • CUse the contingency budget to implement schedule compression.
  • DReassess the issue as part of monitoring and controlling.

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Impediment resolution#Monitoring and controlling#Problem-solving#Adaptive project management
Full PMP PracticeBrowse All PMP Questions