nerdexam
PMI

PMP · Question #1313

An organization imports many of the materials for a product build. Due to global shipping delays, some of the essential materials have yet to arrive, resulting in the inability to finish building the

The correct answer is D. Explore if the materials could be supplied locally and obtained on time.. When essential imported materials are delayed due to global shipping, preventing a product build for an upcoming release, the project manager should recommend exploring local suppliers.

Submitted by devops_kid· Apr 18, 2026Process

Question

An organization imports many of the materials for a product build. Due to global shipping delays, some of the essential materials have yet to arrive, resulting in the inability to finish building the product for the upcoming release. The project manager is meeting with stakeholders to discuss options. What should the project manager recommend?

Options

  • ARequest marketing to launch an advertising campaign for the product that is currently in stock.
  • BUpdate the project management plan, factoring in furloughs of the assembly team to reduce
  • CMeet with the engineering team to manufacture the materials in-house.
  • DExplore if the materials could be supplied locally and obtained on time.

How the community answered

(32 responses)
  • A
    6% (2)
  • B
    16% (5)
  • C
    3% (1)
  • D
    75% (24)

Why each option

When essential imported materials are delayed due to global shipping, preventing a product build for an upcoming release, the project manager should recommend exploring local suppliers.

ARequest marketing to launch an advertising campaign for the product that is currently in stock.

Requesting a marketing campaign for products already in stock does not address the core problem of lacking essential materials for the upcoming release and is an unrelated business activity.

BUpdate the project management plan, factoring in furloughs of the assembly team to reduce

Furloughing the assembly team is a reactive cost-cutting measure that does not solve the material shortage and would further delay production once materials arrive.

CMeet with the engineering team to manufacture the materials in-house.

Manufacturing materials in-house is a significant undertaking that typically requires substantial time, expertise, and investment, making it an impractical short-term solution for an immediate release dependency.

DExplore if the materials could be supplied locally and obtained on time.Correct

Global shipping delays directly impact material availability and production schedules; therefore, actively seeking alternative local suppliers for essential materials is a proactive risk mitigation strategy to keep the project on track for the upcoming release. This directly addresses the constraint caused by the supply chain disruption by looking for an immediate solution to material procurement.

Concept tested: Supply chain risk mitigation

Topics

#Risk Management#Procurement#Issue Resolution#Supply Chain Management

Community Discussion

4
Wei W.Wei W.Nov 21, 2025

D is the right call here. You mitigate the delay by finding an alternate source for the materials locally, which directly addresses the blocker and keeps the release moving, rather than accepting the delay or pivoting to a workaround.

26
Yusuf A.Yusuf A.Dec 5, 2025

Had this one on my exam last month, picked D because a senior PM at my company always says when supply chain breaks, you look for local sourcing before anything drastic like furloughs or in-house manufacturing. C is tempting but manufacturing materials in-house is usually way outside the org's capability, so D is the practical first move.

1
Anjali D.Anjali D.Nov 25, 2025

Our group landed on D. A couple people were tempted by C, but manufacturing in-house is a huge scope change, whereas finding a local supplier is the simplest fix that keeps the release on track.

0
Yusuf A.Yusuf A.Nov 27, 2025

D makes sense for keeping the release on track, but my senior always says to double check whether the question is asking about risk response strategy versus schedule recovery, because D could be mitigate or accept depending on how the answer choices are worded.

0
Full PMP Practice