PMIPMI
PMP · Question #1310
PMP Question #1310: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #1310. The question stem and answer options stay visible for context.
Submitted by miguelv· Apr 18, 2026Process
Question
While managing a project using a hybrid approach, the project manager realizes that there is a high level of rework due to quality issues. Because of that, each feature is taking longer than initially estimated. What should the project manager do to address the issue?
Options
- AAddress the issue during the next sprint planning meeting.
- BExtend the dates for future project milestones.
- CInitiate a change request to extend the project end date.
- DEscalate the issue to the project sponsor.
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Agile Quality Management#Sprint Planning#Rework#Hybrid Project Management