nerdexam
PMIPMI

PMP · Question #1308

PMP Question #1308: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #1308. The question stem and answer options stay visible for context.

Submitted by viktor_hu· Apr 18, 2026Process

Question

A project manager is reviewing the lessons learned for an historical project. The review identifies that the client's engineer was adamant that they review all changes, even those not identified in the contract. How should the project manager deal with this when planning the project?

Options

  • AUpdate the project charter with this information regarding change management.
  • BTalk with the client to ensure they are aware of the change management procedure.
  • CEnsure the change management plan highlights this requirement to prevent future issues.
  • DUpdate the project risk register to identify this risk and describe how to mitigate the issue.

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Lessons Learned#Change Management Plan#Project Planning#Stakeholder Requirements
Full PMP PracticeBrowse All PMP Questions