nerdexam
PMI

PMP · Question #1298

The sponsor approaches the project manager with new features they want added to the project. The project is 95% complete, but the sponsor insists that continued support for the project relies on the a

Sign in or unlock PMP to reveal the answer and full explanation for question #1298. The question stem and answer options stay visible for context.

Submitted by fatima_kr· Apr 18, 2026Process

Question

The sponsor approaches the project manager with new features they want added to the project. The project is 95% complete, but the sponsor insists that continued support for the project relies on the addition of the new features. What should the project manager do?

Options

  • AImplement the new features after assessing the impact.
  • BReject the new features since it amounts to gold plating.
  • CAssess the impact of the features and refer it to the change control board (CCB).
  • DAdd the new features to avoid losing the sponsor's support for the project.

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Change Control#Scope Management#Stakeholder Management#Integrated Change Control
Full PMP Practice