PMP · Question #1287

A project manager was recently assigned to a new project that is about to start. The organization has already signed a fixed-cost contract with the customer detailing the scope and final delivery date

The correct answer is C. Create a contingency plan in case the project deviates from the initial plan.. Given identified constraints that will prevent the project from meeting planned iterations, the project manager should create a contingency plan to address deviations and ensure contractual obligations are met.

Submitted by carter_n· Apr 18, 2026Process

Question

A project manager was recently assigned to a new project that is about to start. The organization has already signed a fixed-cost contract with the customer detailing the scope and final delivery date, but the project manager has identified several internal constraints and conditions that will certainly prevent the project from being completed in the number of iterations initially planned. What should the project manager do next?

Options

  • ACreate an issue log template that will be used to identify and track impediments.
  • BCreate a schedule management plan to ensure the project meets the delivery date.
  • CCreate a contingency plan in case the project deviates from the initial plan.
  • DCreate an assumption log and map assumptions to impediments based on the impact to the

How the community answered

(32 responses)
  • A
    16% (5)
  • B
    6% (2)
  • C
    56% (18)
  • D
    22% (7)

Why each option

Given identified constraints that will prevent the project from meeting planned iterations, the project manager should create a contingency plan to address deviations and ensure contractual obligations are met.

ACreate an issue log template that will be used to identify and track impediments.

Creating an issue log template is a general project setup activity, but it does not proactively address the known, high-probability failure of the initial plan due to identified constraints.

BCreate a schedule management plan to ensure the project meets the delivery date.

Creating a schedule management plan is part of project planning, but the core issue is that the *existing* schedule plan is deemed unachievable, necessitating a strategy to manage that deviation rather than just documenting scheduling processes.

CCreate a contingency plan in case the project deviates from the initial plan.Correct

When a project manager identifies internal constraints that 'certainly prevent' the project from being completed as initially planned, despite a fixed-cost contract and delivery date, a significant risk to project success exists. The most immediate and crucial next step is to create a robust contingency plan. This plan outlines specific actions, resources, and alternative strategies to be implemented if these anticipated deviations occur, aiming to mitigate their impact and ensure the project still meets its contractual scope and final delivery date.

DCreate an assumption log and map assumptions to impediments based on the impact to the

While an assumption log tracks assumptions, the project manager has *identified* constraints that 'certainly prevent' success, moving beyond mere assumptions to known problems that require a direct mitigation strategy like contingency planning.

Concept tested: Risk management, contingency planning, fixed-cost project management

Topics

#Risk Management#Contingency Planning#Constraint Analysis#Proactive Planning