nerdexam
PMIPMI

PMP · Question #1287

PMP Question #1287: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #1287. The question stem and answer options stay visible for context.

Submitted by carter_n· Apr 18, 2026Process

Question

A project manager was recently assigned to a new project that is about to start. The organization has already signed a fixed-cost contract with the customer detailing the scope and final delivery date, but the project manager has identified several internal constraints and conditions that will certainly prevent the project from being completed in the number of iterations initially planned. What should the project manager do next?

Options

  • ACreate an issue log template that will be used to identify and track impediments.
  • BCreate a schedule management plan to ensure the project meets the delivery date.
  • CCreate a contingency plan in case the project deviates from the initial plan.
  • DCreate an assumption log and map assumptions to impediments based on the impact to the

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Risk Management#Contingency Planning#Constraint Analysis#Proactive Planning
Full PMP PracticeBrowse All PMP Questions