PMI
PMP · Question #1268
A project manager is working on a project using a hybrid approach. The project is scheduled to be completed in three more sprints. One of the team members notifies the project manager that they are le
Sign in or unlock PMP to reveal the answer and full explanation for question #1268. The question stem and answer options stay visible for context.
Submitted by anna_se· Apr 18, 2026Process
Question
A project manager is working on a project using a hybrid approach. The project is scheduled to be completed in three more sprints. One of the team members notifies the project manager that they are leaving the company, which was approved by their functional manager. What should the project manager do first in this situation?
Options
- AAsk the functional manager for an immediate replacement for the team member.
- BReview the risk management plan and mitigation plan to understand the impact of this issue.
- CAsk the functional manager why a decision was made without consulting them.
- DUse soft skills to influence the team member to stay until the project is completed.
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Risk Management#Resource Management#Issue Management